Contruction of The CENTER December 2001 - July 2002
|
 November 2001 - Preconstruction
|
 December 2001 Pier and poured wall construction with interior excavating |
 January 2002 Additional piers, grading
|
|
 February 2002 Foundation walls and pier lines
|
 March 2002 Steel goes up at the CECC site |
 April 2002 Roof construction and brickwork in progress |
|
 May 2002 The front entrance takes shape |
 June 2002 The windows go in |
 July 2002 Construction complete |
|